Capital Reserve Project Update
December 2025
Included Projects:
- Phase 1 - Sed Permit Issued
- Installation of Field Lighting on Mezaros
- Replacement of the Turf on Mezaros
- Resurfacing of the Oley Track
- Removal of Casework in some High School Classrooms
- Replacement of some Ground Floor Windows at the Middle School for Safety Reasons
- Bathroom Upgrade of the First Floor Girls Bathroom in the High School
- Phase 2
- Paving of the Basketball Court on the Dows Lane Campus
- Paving of the Play Area at Dows Lane on the East Side of the Building
Bids:
- Electrical Bid to Support Field Lighting Project Received November 19 and to Be Awarded December 2
- Bid Specifications for the Remaining Phase 1 Projects Are Currently Being Finalized
Timeline Updates:
- Weather Permitting, Field Lights Installation to Be Completed by March 15, 2026
- Track and Field Replacements Work to Begin in June 2026 After Spring Season Is Complete
- Remaining Phase 1 Work to Be Completed Summer 2026